Quantcast
Channel: FP McCann
Viewing all 620 articles
Browse latest View live

Supporting role for FP McCann’s precast columns in new International Quarter, London

$
0
0

Site: International Quarter, Stratford, London

Contractor: PJ Carey Ltd.

Client: Lendlease / London & Continental Railways JV

Products Supplied: Precast concrete columns from 1.5 to 19 tonnes

FP McCann’s specialist precast division has recently completed the manufacture and delivery of over 1,000 precast concrete columns forming part of the superstructure for two prestigious commercial buildings in Stratford, East London.

Situated on a 22 acre site within the Olympic Park is Stratford’s International Quarter, a £2.3 billion commercial and retail development creating a new metropolitan centre in London. FP McCann supplied the precast columns for two of the buildings, S5 and S6, which have already been let to high profile tenants, Transport for London (TFL) and the Financial Conduct Authority (FCA). Building frame contractor PJ Carey Ltd, awarded the contract to supply the precast columns to FP McCann, due to past collaboration on another high specification project at Chiswick Park. 

FP McCann was tasked with manufacturing 1000 plus structural precast columns to a very unique design mix. The mix had to provide a compressive strength of over 80 kN/mm2 on building S6 (11 levels) and 90kN/mm2 building S5 (19 levels). 

Aside from the high specification on concrete design strength, the columns are an architectural feature and required a finish to complement the exterior designs. As such, the factory fnish of the columns was of a very high standard, with individual units being required to meet the architectural specification straight out of the moulds at Littleport. All units were subject to individual inspection and final client sign-off.

The weight of the columns range from 1.5 tonnes to 19 tonnes; the largest column cast as a single piece is a double height unit which spans from the ground floor to the 1st floor, via the mezzanine level, and measures less than 12 metres.  During construction, PJ Carey installed the columns at a rate of one level every 8 days, and just-in-time deliveries were required, due to the limited space on-site. The two buildings were successfully delivered to program; both the client and the architect are extremely pleased with the products provided.

Patrick Sexton, FP McCann’s Specialist Precast General Manager says,“Due to our high profile and successful involvement in supplying the special precast columns to Buildings S5 and S6 in The International Quarter, with another nine buildings to be completed between 2017 and 2025, we are very optimistic about securing further work on this prestigious urban development.”

For further information on FP McCann’s specialist precast solutions, contact the team at Littleport on 01353 861416 | sales@fpmccann.co.uk

  • FP-McCann-Precast-Specialist-Columns

Considerate Constructors Awards 2017

$
0
0
On the 21st March 2017, FP McCann attended the Considerate Constructors National Site Awards held in the Lowry Hotel, Manchester. The Considerate Constructors Scheme’s National Site Awards recognise those sites registered with the Scheme that raised the bar for considerate construction.  
 
The Considerate Constructors Scheme looks at the measures a site has taken to be more considerate towards local neighbourhoods and the public, the workforce, and the environment.  On this occasion FP McCann secured two awards, a Silver award for their work on Newtownards Public Realm, and a Gold award for their work on Magherafelt Public Realm.
 
 
 
For Newtownards Public Realm, the scheme assessors noted that the site had demonstrated an extraordinary commitment to improving the image of construction through adhering to the scheme’s five-point code of considerate practice: Care about Appearance, Respect the Community, Protect the Environment, Secure everyone’s Safety, and Value their Workforce. For Magherafelt Public Realm, the scheme assessors noted that the site continued “to impress as a first-class approach to Public Realm Environmental Improvement Works in a very busy town centre setting”. 
 
Winning a National Site Award is an exceptional achievement, and recognises those sites that have made the greatest contribution towards improving the image of construction within the UK, and reinforces FP McCann’s commitment over the last number of years to not only provide top quality projects and exceptional service to its clients but also to be at the forefront of helping change today’s image of construction. 
 
 
These are tremendous achievements for the company, and especially for those working in the Public Realm sector. Congratulations to both teams who worked on these projects for their time and extra effort in making these awards happen. 
 
  • FP-McCann-Considerate-Constructors-Scheme-Awards

Business Administration Apprentice

FP McCann's shaft segments and cover slab form pump house for Wessex Water Scheme

$
0
0

 

Site: Pump House, Yeovil

Contractor: Terra Solutions

Client: Wessex Water

Products Supplied: Precast concrete back-bolted caisson shaft segment rings, reinforced concrete cover slab

 

As part of a Wessex Water capital scheme to boost waste water services to the increasing population in and around the Somerset town of Yeovil, FP McCann’s back-bolted caisson shaft segment rings have been used to build a 7.50m id pumping station chamber.

The contract to build the shaft and other associated civil engineering works was awarded to Terra Solutions, one of the UK and Ireland’s leading trenchless contractors, specialising in tunnelling and pipe repair.
 
The shaft was sunk under its own weight using the caisson method and the shaft wall was formed using 8 no. FP McCann 7.50m ID back-bolted standard precast concrete rings. The steel cutting shoe was installed by Terra. Prior to the pouring of a concrete guide collar around the outside of the segments, the base segmental ring was constructed and a second ring was placed on top. Once the collar gained the required strength, the third ring and subsequent rings were placed on top, thereby allowing the shaft to sink under its own weight.
 
Once the shaft build was completed, concrete was poured into the base to form a 1.5m deep plug, and a further 500mm reinforced concrete base was pumped in, dowelled and tied to the shaft wall to complete the solid chamber.
 
To complete the watertight pumping chamber build, FP McCann supplied the reinforced concrete cover slab. This was delivered in three sections, the heaviest of which weighing just over 20 tonnes.
 
 
Commenting on the shaft build, Warren Patton of Terra Solutions said, “The concrete segments supplied by FP McCann were connected on site and each ring descended under its own weight as the ground was excavated beneath. Once commissioned this 8 metre deep chamber will significantly add to the capacity to manage the waste water in Yeovil”.
 
 
Key features and benefits of FP McCann’s back and front bolted smoothbore shafts are:
 
• Smooth internal faces
• Simple locking process
• Speedy installation
• Increased site productivity
• Safe build features
• Technical advice and support
 
For tunnels & shaft enquiries, please contact our Cadeby office on 01455 290780 or email: sales@fpmccann.co.uk
  • FP McCann cover slab

Quantity Surveyor

Project Co-ordinator – Walling Products

FP McCann’s Headwalls used on large distribution development in Derbyshire

$
0
0

Site: Foston, Derbyshire

Contractor: GF Tomlinson & Sons
 
Client: ATL Warehousing & Distribution
 
Products Supplied: Precast concrete Headwalls
 

Derbyshire based construction company, GF Tomlinson & Sons, are utilising FP McCann's small, medium and large precast concrete headwalls  as work starts on a new £6m depot facility in Foston, Derby

GF Tomlinson is building the 190,000 sq ft centre for haulage business ATL Warehousing and Distribution on their 25-acre site in Woodyard Lane, Foston. The family-run company is investing in the site after experiencing a number of years of organic growth. Work on the new building, which will provide storage for 22,000 pallets of goods, is expected to be completed by the end of September.

Part of the contract in building the new distribution hub involves draining excess storm water from the site and directing the outfall into the natural watercourse surrounding the development. To incorporate the SuDS type drainage into the scheme, a 120 metres swale to the rear of the building has been constructed. Along the length of the swale, GF Tomlinson has installed 7 FP McCann  precast concrete headwalls ranging from three small headwalls accommodating a 150mm diameter pipe outlet, to two of the large standard headwalls with a 825mm diameter pipe outlet. The outlet points to the large headwalls  are all fitted with galvanised safety grating.

Commenting on the headwall installation Phil Childs, Projects Manager for GF Tomlinson & Sons says, “We chose the FP McCann standard precast concrete headwalls for their speed of installation and to help reduce the environmental impact at ground works stage. The headwalls were placed in-situ without the need for extensive excavation of the swale embankment. No shuttering or formwork was required and in particularly wet conditions they are an ideal off-site manufactured outfall solution”.

FP McCann is also supplying standard spigot and socket precast concrete pipes and manhole chamber rings to the Foston contract.
 
Note:
FP McCann’s standard headwall designs and a selection of bespoke units, together with lifting and installation guidelines, are available for download. fpmccann.co.uk/headwalls
 
For GB Drainage enquiries, please contact our Ellistown office on 01530 240000 or email: sales@fpmccann.co.uk 
  • FP-McCann-Precast-Drainage-concrete-headwalls

Maintenance Electrician


Construction and Engineering Careers and Training Information day

$
0
0

Meet College Staff, Local Employers and Companies looking for new talent!

This event is aimed at school leavers, existing students, parents and those looking for information on careers and training in growth industries.

Venue: Northern Regional College, Magherafelt Campus

Date: Saturday 24th June 2017

Time: 11am-1pm

 

Graduate Software Developer

$
0
0

This is an opportunity for a new or recent IT graduate interested in starting their career in a busy IT department, supporting the needs of an innovative manufacturing organisation. The position will best suit someone who is a driven and motivated individual who likes to ask questions and wants to become a key part of a dynamic development team. The I.T. department develops and supports systems which are integral to every aspect of the company’s operations including Design, Manufacturing, Transport, Sales, HR and Finance. The successful candidate will eventually be responsible for developing, delivering and maintaining high quality software solutions for the organisation.  

Job Type: 
Jobs (including graduate opportunities)
Closing Date: 
Friday 30th June 2017

Portadown Linkages update - Public Realm

$
0
0

Project Start Date: 13th February 2017

Project Completion Date: Mid-Autumn 2017

Project Funders: Armagh City, Banbridge and Craigavon Borough Council and the Department for Communities 

 

The Portadown Linkages Project aims to improve the linkages and connections surrounding Portadown town centre, including the People’s Park, Portadown train station, ASDA, the Meadows Shopping Centre, the Old Town Quay river access scheme and the town centre.

 

FP McCann has been appointed as the main contractor for the project. We have extensive experience in successfully completing public realm work of this size and scale throughout Northern Ireland. Our most recent public realm projects include Magherafelt, Cookstown, Newtownards, Comber, Donaghadee, Bangor and Holywood. 
 
Progress to date
Investigative works have been completed across the seven areas.
 

The work has been completed onCraigwell Avenue ahead of schedule, and works are continuing on Castle Street, Woodouse Street, West Street, Meadow Lane and Carrickblacker Road Junction.

Upcoming works
Obins Street and Park Road are due to commence after the July holidays. 
 
This scheme is a major civil engineering project with significant quantities of material transported in and out of the seven separate locations across Portadown. We will endeavor to complete the works as efficiently as possible and minimise any disturbance caused to you as a resident, business or customer. During work:
  • All areas will remain open for business throughout.
  • Pedestrian access will be maintained to all businesses and properties.
  • Some parking bays may be closed to facilitate construction, however this will be a temporary measure and any impacts will be kept to a minimum.
  • It is anticipated that works will be complete by mid-Autumn 2017.
We are confident that you will see a significant improvement to the current streetscape that will ultimately deliver a positive impact on the linkages and town as a whole and we thank you for your patience and co-operation during this construction phase.
 
 
 
 
 
 
CONTACT DETAILS:
 
FP McCann Ltd has appointed a dedicated Public Liaison Officer for this scheme, Dianne Kelly, who will act as a point of contact during the works for residences, businesses and any other interested parties. Contact details for the site team are listed below:
  • Call Dianne Kelly, Public Liaison Officer Tel: 077 1091 6133
  • Visit our site office located at 68A Church Street, Portadown
  • Call our 24hr site contact number Tel: 028 7954 9090 (option 1)
  • Email your queries to pdnl@fpmccann.co.uk 

 

  

 

 

  • FP-McCann-Civil-Engineering-Portadown-Linkages-Public-Realm

FP McCann's Precast Concrete Vehicle Docking System installed at new Screwfix distribution facility

$
0
0
Site: Fradley Park, Lichfield, Staffs
 
Contractor: Winvic Construction / Prologis
 
Client: Screwfix
 
Products Supplied: Precast Concrete Docking System
 
FP McCann’s specialist precast concrete installation team has recently completed the build of a multi-vehicle docking system on a brand new 562,000ft2 distribution centre in Fradley near Lichfield, Staffs. Once opened in October this year, the ‘large shed’ distribution facility build will provide warehousing and a central transport hub for Screwfix, the UK’s largest distributor of hardware and plumbing products. The £20 million DC1 project is being undertaken by Winvic Construction, on behalf of logistics property developer Prologis, and is one of many Staffordshire dock system jobs FP McCann has recently supplied and installed in partnership with Winvic.
 
 
FP McCann delivered a package of off-site manufactured precast docking system products designed for speedy, efficient and safe installation. The new warehouse will provide loading dock leveller ramps for up to 80 vehicles at any one time. Each dock leveller ramp is fully supported by a precast concrete dock leveller pit. The precast pits are formed from a combination of front walls, retaining walls and biscuit slabs. The biscuit slab spans from the front wall to the rear retaining wall to form an opening for the dock leveller ramp to sit in. These panels form a continuous precast structure for multiple pit installations. Above the dock leveller pits are 336 linear metres of insulated double prowall panels. Each panel is 8m long x 3.8m high, weighs over 7 tonnes and is supplied complete with 2nr 3.00m x 3.00m openings for access. Installation of the dock leveller pits and insulated prowall panels was completed over a 3 week period.
 
Transported from the Company’s Byley facility in Cheshire, the dock leveller pits, together with the large double prowall panels and door openings, were delivered to site on a just-in-time delivery schedule. Once on site, the walls and panels were lifted from the vehicles and placed into position in one single, safe operation. The panels were then secured to the building’s steel frame.
 
 
Commenting on the construction, Nick Lakin, Project Manager for Winvic at Fradley says,“This precast concrete system lends itself in particular to a safe and efficient build. Speed of installation means that vehicles can be quickly turned around and no site stocking of product is necessary. FP McCann’s fixing team are fully versed in this docking system, and their working method complements the Winvic site construction practices. Utilisation of the FP McCann precast docking system dramatically reduces the installation time when compared to more traditional construction methods. Offsite manufacture in a factory controlled environment also improves the quality of the finished building and reduces exposure to onsite risks such as health and safety factors and the weather”.
 
 
For Dock Leveller enquiries, please contact our Weston Underwood office on  01335 361269 or emailsales@fpmccann.co.uk

 

  • FP-McCann-Precast-Concrete-Dock-Levellers

Apprentice in Professional Construction

Production Operatives

FP McCann’s Specialist Precast division provides innovative solution for Kent Beach access scheme

$
0
0
Site: Shakespeare Beach, Dover, Kent
Client: Network Rail
Contractor: Costain (South East Multifunctional Framework)
Scheme Engineer: Tony Gee and Partners
Products supplied: Bespoke Precast Stairs and Modular Substructure
 
 
Following a severe storm in December 2015, resulting in the partial collapse of 250 metres of sea wall and associated damage to the main Dover to Folkestone rail line, a 9 month programme of major work has been undertaken at Shakespeare Beach. Costain, the South East Multifunctional Framework partner to Network Rail, has constructed a 235 metres viaduct above the damaged wall, supported on 130 concrete columns. Additionally, in excess of 100,000 tonnes of rock armour stone imported from Norway has been placed to act as a breakwater in front of the existing failed wall.
 
The storm also washed away up to 2 metres of the beach and, as part of the overall scheme; there was a requirement to rebuild a public right of way from a footbridge at Wellards Way down to Shakespeare Beach, in the form of a new set of steps down through the rock armour.
Due to the significant issues involved with constructing something suitable in-situ, Costain contacted FP McCann to investigate an innovative approach in collaboration both with themselves and principal engineer Tony Gee and Partners using an off-site precast concrete system.
FP McCann was asked to develop a modular precast substructure to act as permanent formwork and support for the concrete stair flights already detailed by TGP. This modular structure took into account the logistical challenges in the transportation of the units, the lifting arrangements, and enabled the structure to be erected and secured in the short intertidal periods available for construction.
 
 
 
The precast concrete stair flight which FP McCann also supplied is buttressed on either side by the armour stone. The steps have been given an anti-slip surface by shot blasting, all undertaken offsite at FP McCann’s factory in Littleport, Cambridgeshire.
To allow for long term public access, the installed structure has made provision for the future erosion of the beach by extending well below the current beach level.
 
Commenting on the project Patrick Sexton, General Manager for FP McCann’s Specialist Precast Division, remarked“We worked closely with the Costain project team and our engineers Pick Everard, to provide a workable and practical solution, both from a manufactured and installed system perspective. This resulted in a successful conclusion to a logistically demanding project”.
 
 
 
Ian Arden Senior Agent for Costain on the scheme said, “As part of the Dover Sea Wall project, we were instructed to build a set of stairs to the beach. These steps had to be constructed in the intertidal zone, giving a working window of as little as 3 hours. FP McCann worked closely with Costain to develop a modular staircase utilising both standard and bespoke products. FP McCann’s engineered precast concrete structure accounted for both temporary and permanent load cases and met our detailed installation requirements. Their fabrication team were able to turn the production around very quickly, aligning to the site requirements and delivering the modules in a ‘just-in-time’ manner. FP McCann worked as a true partner throughout and their contribution was key in the delivery of this element of the project”.
 
For more details about FP McCann’s Specialist Precast Solutions, contact a member of our Littleport team on 01353 861416 or email: sales@fpmccann.co.uk
  • FP-McCann-Precast-Concrete-Specialist-Solutions

Reduced pipe bedding initiative used on West Yorkshire housing development

$
0
0
Site: Roundhay, Leeds, West Yorkshire
Client: Chartford Homes
Contractor: Athena Civil Engineering
Products supplied: Large diameter precast concrete pipe stormwater management system
 

Leeds based ground worker and civil engineer, Athena Civil Engineering, has taken the initiative on a new housing development in Roundhay, near Leeds, to reduce the amount of primary aggregate used on the pipe drainage works. This is in line with industry guidelines which indicate that using a full surround class ‘S’ granular bedding in conjunction with large diameter precast concrete pipes is often over specifying the buried pipeline design.

Working on behalf of housing developer Chartford Homes at their new Hampton Park site, Athena has constructed a storm attenuation tank using FP McCann’s large diameter reinforced concrete spigot and socket pipes. By adopting a class ‘B’ embedment design, Athena has achieved significant cost savings and minimised environmental impact on site without sacrificing installed performance of the completed pipe system.  

The attenuation tank set out in four pipe runs consists of 21 standard DN1800 2.5 metre spigot and socket pipes, 4 DN1800 pipes with end caps and 4 DN1800 pipes with end caps and cast in side entry access.

Using the Concrete Pipeline Systems Association (CPSA) structural design and material cost calculators based on BS 1295-1 “The structural design of buried pipelines”, Athena were able to determine the optimum bedding design to adopt for the project and calculate the cost benefits versus a plastic system with a full Class ‘S’ granular surround. Key inputs into the model included pipe sizes and comparative costs and imported granular material prices. Consideration was also given to the trench excavated material which was deemed suitable for final backfill purposes. 

Commenting on the installation, Jonathan Hotham, Project Manager for Athena Civil Engineering said, “We had every intention of using plastic pipe on this project, but when FP McCann’s Area Manager, Igor Skoro, took us through the CPSA structural design and material cost calculators, it gave us the opportunity to present a more cost-effective and efficient approach to the job for our client and builder, Chartford Homes, who took on board our proposal. We shall certainly be using the CPSA material cost calculator on future schemes and a closer consideration of pipe choice, in conjunction with bedding options, will be something we’ll continue to develop.”

The CPSA Structural Design Calculator can be accessed via www.concretepipes.co.uk /calculators/material-cost

For enquiries, contact;
 
GB Precast Drainage Solutions;      
Sales team: 01530 240000 | sales@fpmccann.co.uk
 
NI/ROI Precast Drainage Solutions;
Sales team: 028 7954 9026 | sales@fpmccann.co.uk
  • large-diameter-precast-concrete-pipe-stormwater-management-system

Senior Engineer

$
0
0
As a member of the Technical Department, the role is involved with the design of a wide range of precast concrete products, generally associated with civil engineering projects, but also involved with prestressed concrete and modular building systems.  The team includes Engineers and Technicians, and activities are based around specific projects or standard product ranges.
 
The Technical Department engages with all divisions of the company, providing technical and structural input in support of existing products and new product development.
 
The role requires the person to be a highly motivated individual with initiative, self-confidence, excellent communications skills, flexibility and adaptability, with the drive and ability to work under their own direction or within a small team of professionals. Be keen to develop their individual capability and that of the team.  Lead by example, in terms of behaviour.
 
Ideally, a Chartered or near Chartered Engineer with experience of precast concrete design.
Job Type: 
Jobs (including graduate opportunities)
Closing Date: 
Sunday, 13th August 2017

FP McCann’s Precast Concrete Fencing Division goes from Strength to Strength

$
0
0

Since its formation some 9 years ago, FP McCann’sfencing division has firmly established itself as a leading UK supplier of precast concrete posts, panels and gravel boards. Significant capital investment and key strategic commercial recruitment is set to take the business to the next level. 

Operating out of its Cadeby manufacturing facility near Nuneaton, Warwickshire, the company is ramping up production this year by an additional 30% with a £2.5 million investment in two new Coote precast concrete production lines; the first of which will be operational from this month. In addition to increased productivity levels, the other major benefits of the new lines will be enhanced quality of the finished products and a reduction in the requirement for on-site manual handling. To accommodate the increase in production capacity at Cadeby, FP McCann is also increasing its on-site stocking capabilities with the acquisition of an additional 22 acres for hard standing.

“Having an extensive product range in stock will enable us to smooth out the natural annual ‘peak and trough’ demands particular to the UK fencing products market”, comments Katie McGorty (pictured right), FP McCann’s National Fencing Sales Manager. “Providing quality products straight from stock at a competitive price is key to the future growth of our fencing business”, Katie adds. 

FP McCann is also strengthening its commercial presence following the recruitment of two key people: Lisa Mackett, formerly of Supreme Concrete, has now joined the FP McCann fencing team with sales management responsibilities in the South, South-East and London areas; and Jack Wheldon, who is coming in from the Forterra Building Products group to take up the position of Area Sales Manager in the South-West region. “With Lisa’s extensive 20 years knowledge and experience into the precast fencing industry, we are looking forward to expanding our strategic coverage with stockists and contractors alike. Jack’s background at Forterra dealing with the building sector also makes him an extremely valuable addition to our team, Katie says. 

FP-McCann-Precast-Concrete-Fencing-Cadeby

Lisa Mackett                                                                   Jack Wheldon

The Cadeby operational and commercial teams are well positioned not only geographically, but with a bank of skills and knowledge gained from years of experience and FP McCann's willingness to invest in its business divisions, it will ensure the company is at the forefront of the precast concrete fencing sector in years to come

Lisa and Jack join David Harper, Area Sales Manager for the Midlands region. David can be contacted on 07921 108524 or email: dharper@fpmcccann.co.uk

Lisa Mackett

Jack Wheldon

Area Sales Manager   

Fencing and Building Products

-South East

Phone07738 604829

Email: lmackett@fpmccann.co.uk

Area Sales Manager   

Fencing and Building Products

-South West

Phone07736 464612

Emailjwheldon@fpmccann.co.uk

For Fencing enquiries, please contact our Cadeby office on 01455 290780 or emailsales@fpmccann.co.uk    

  • FP-McCann-Precast-Concrete-Fencing-Cadeby

Design Engineer

$
0
0
As a member of the Grantham Design Department, the role is involved with the design and detailing of walls/panels/cross-wall projects. The team includes Engineers and Technicians, and activities are based around projects being tendered and active schemes. 
 
The design department provides structural input in support of this product group, liaising both internally and externally with clients and engineers. 
 
The role requires the person to be a highly motivated individual with initiative, self-confidence, excellent communications skills, flexibility and adaptability, with the drive and ability to work under their own direction or within a small team of professionals. Be keen to develop their individual capability and that of the team. Lead by example, in terms of behaviour. 
 
Ideally, a Graduate Engineer with experience of concrete design. Experience within a precast concrete environment would be beneficial.
 
Job Type: 
Jobs (including graduate opportunities)
Closing Date: 
Sunday, 13th August 2017

CAD Technicians

$
0
0
This role is involved with the design and detailing of a range of precast concrete products, generally associated with civil engineering projects. The team includes Engineers and Technicians, and activities are based around specific projects or standard product ranges.
 
Closing Date: 
Sunday, 13th August 2017
Viewing all 620 articles
Browse latest View live